Construction Notice #63: Port Lands Flood Protection & Lake Shore Boulevard East Projects

Body

November 2025

Construction Manager: EllisDon

 

Traffic Notice

 

Don Roadway South to Open in November  

As of mid-November, Don Roadway South will open to pedestrians, cyclists, and drivers. The newly constructed roadway has been raised to a higher elevation for flood protection and redesigned with dedicated pathways for walking and cycling, providing a new connection to Biidaasige Park. Turn restrictions will be in place at Lake Shore Boulevard East and Don Roadway until the end of 2025. 
 

Traffic restrictions are as follows (see map below for reference):  
 

Going Eastbound:  

  • Left turns onto the DVP ramp will be restricted
  • Right turns onto Don Roadway are permitted

Going Westbound  

  • Left turns onto Don Roadway will be restricted
  • Right turns onto the DVP ramp are permitted  

Going Northbound  

  • Northbound onto the DVP will be permitted
  • Left turns on to LSBE westbound is permitted
  • Right turns onto LSBE eastbound is permitted  


These temporary turn restrictions are in place to support the completion of remaining work on the Lake Shore Bridge and the construction of the median. They are expected to be lifted in December 2025, when the project reaches substantial completion. 

 

All work on Lake Shore Boulevard between Carlaw Avenue and the Lake Shore Bridge is expected to be complete by the end of 2025. Once finished, Lake Shore Boulevard will feature three lanes in each direction, enhanced landscaping, and improved facilities for pedestrians and cyclists. 
 

Image
An aerial view of the Lake Shore Boulevard East and Don Roadway intersection, illustrating the turn restrictions.

Above: an aerial photo of the Lake Shore Boulevard East and Don Roadway intersection, illustrating the turn restrictions.
 

Questions? 

To learn more about this project, please visit the Lake Shore Boulevard East Project Webpage.

To send us questions or concerns about construction, use this online inquiry form. You can also email us at plfp@ellisdon.com

For urgent construction related issues, please contact Kevin Cassar, EllisDon, at 416-594-2198.