Addendum #3 - Request for Proposals: 2027 Floating Public Art Harbour Square Park Basin
November 27, 2026
Enquiries
The following enquiries have been received, and responses have been provided for clarification and information purposes.
Question 1:
Can an artist use similar community-engagement processes and materials in the proposed artwork and in future works, provided the resulting artworks are conceptually and aesthetically distinct?
Answer 1:
Section 6.12 is intended to preserve the uniqueness of the commissioned artwork, not to restrict an artist’s creative processes or future artistic practice. Please also refer to Addendum #1 for further clarification.
Question 2:
Can materials or outcomes generated through the commissioned project be used to create new work in the future, provided the commissioned artwork itself is not reproduced?
Answer 2:
Materials from the commissioned artwork may be reused or repurposed in future works, provided the resulting work is materially different and does not reproduce the commissioned artwork. Waterfront Toronto encourages sustainable practices, including the reuse and repurposing of materials following the exhibition. Applicants are encouraged to describe their proposed approach in the Sustainability Statement included with their submission.
Question 3:
Can an U.S.-based artist based apply as part of an artist team that includes a Canada-based artist and uses Ontario-based contractors, including where the U.S.-based artist is the lead artist?
Answer 3:
In accordance with Section 1.1 of the RFP, Waterfront Toronto reserves the right not to enter into a contract or agreement with U.S.-based firms for the services and deliverables required under this RFP.
Question 4:
How does the Business Location Attestation in Appendix E apply where the lead artist or a member of the artist team is based in the U.S.?
Answer 4:
A Canadian artist may include a U.S.-based artist or practice on the broader project team, provided the Canadian artist is the applicant and contracting party with Waterfront Toronto and meets the eligibility requirements of the RFP.
Question 5:
Can a Canadian artist submit a collaborative proposal with a U.S.-based creative partner? Would eligibility differ if the U.S.-based party is a named co-artist or collaborator versus a paid consultant or subcontractor?
Answer 5:
A Canadian artist may include a U.S.-based artist, architecture/design practice or other creative professional on the broader project team, provided the Canadian artist is the applicant and contracting party with Waterfront Toronto and meets the eligibility requirements of the RFP.
A U.S.-based practice may also be retained by the Canadian artist as a design or creative consultant or subcontractor. Whether the U.S.-based party is described as a “co-artist” or “creative partner” does not determine eligibility; what matters is the legal and contractual structure of the proposed team. If the U.S.-based party forms part of the applicant or contracting entity, Waterfront Toronto cannot confirm eligibility in advance. The proposed arrangement must satisfy the eligibility requirements of the RFP, including the Business Location Attestation requirements.
Waterfront Toronto does not prescribe or recommend a preferred team structure. Applicants are responsible for determining the composition and contractual structure of their project teams and ensuring compliance with all applicable RFP requirements, including those related to Ontario-based contractors and professional services.
Question 6:
Can standard 120V AC power be supplied to the floating artwork from shore, including by means of a suitably rated underwater cable?
Answer 6:
There is no electrical infrastructure available at the project site. Solar-powered lighting is permitted but is not required as the exclusive power source. Any proposed lighting and power system must be suitable for the marine environment and comply with applicable safety and navigation requirements, subject to review by the relevant authorities.
Navigation safety lighting is required, as outlined in Section 2.2.1 of the RFP. The RFP does not prescribe a specific fixture type or lighting standard. Proposed lighting should provide appropriate visibility for navigation while minimizing light pollution and disturbance to nearby residents.
Question 7:
Can a Canadian-based business act as the applicant, curator and contracting entity in partnership with an international artist? Would this arrangement meet the RFP’s eligibility requirements?
Answer 7:
The RFP is open to professional artists and artist teams based in Canada. An eligible Canadian applicant may include an international artist on the broader project team, provided the Canadian party is the applicant and contracting party with Waterfront Toronto and meets the eligibility requirements of the RFP. The proposed arrangement must also satisfy the Business Location Attestation requirements in Appendix E.
Question 8:
Are existing or ready-made artworks eligible for submission, including artworks fabricated outside Ontario and subsequently shipped to Toronto for installation?
For existing or ready-made artworks, what requirements apply to the use of Ontario-based contractors or subcontractors for installation and removal?
Answer 8:
Existing artworks are eligible for submission. A ready-made or pre-existing artwork may have been created outside Ontario and shipped to Toronto for installation. If new fabrication or adaptation is required specifically for this opportunity, Ontario-based contractors must be used.
Ontario-based contractors are also required for the applicable technical delivery of the project, and the use of local subcontractors is strongly encouraged.
Question 9:
Are there any exclusion zones, restrictions on the number or location of anchor points, or preferred anchoring areas within Harbour Square Park Basin that applicants should consider when developing their proposed anchoring approach?
Answer 9:
The RFP does not prescribe a maximum number of anchor points or a preferred anchoring layout. Artists should develop an anchoring approach appropriate to the proposed artwork, ensuring the installation remains within the basin and does not obstruct navigation or create safety hazards. The final anchoring configuration will be refined following selection and will be subject to marine engineering requirements and review by the Harbour Master’s office and other relevant authorities.
Question 10:
Is there a required standard or fixture type for navigation safety lighting? Is solar power required, or can other suitable power sources be proposed?
Answer 10:
Section 2.2.1 does not prescribe a specific fixture or lighting standard. Navigation safety lighting is required, and any additional markers or buoys will be determined as needed. There is no electrical infrastructure available at the site. Solar power is permitted but is not the only allowable power source. Any proposed lighting and power system must be suitable for the marine environment and comply with applicable safety and navigation requirements, subject to review by the relevant authorities.
Question 11:
During the exhibition period, can the artist team access the artwork by boat for inspection and maintenance? Are there designated access points, launch locations or scheduling requirements that should be considered?
Answer 11:
The artwork must be accessible by boat where inspection or maintenance is required. There is no designated launch point or maintenance window at this stage; access arrangements will be coordinated following selection. As outlined in Section 2.2.1, the artwork must also be designed to preclude climbable activity and include appropriate warnings against climbing or tampering. Artists are responsible for ensuring that their proposed design, installation and maintenance approach complies with all applicable RFP requirements. Final arrangements will be subject to the necessary engineering reviews, approvals and permitting processes.
Question 12:
Are there preferred areas within the basin for the artwork, minimum setbacks from dock walls or decks, or areas that must remain clear for navigation?
Answer 12:
There is no prescribed zone or minimum distance from the dock walls. The artwork must remain within the basin and must not obstruct navigation or create a safety hazard. Final positioning will be reviewed as the design develops.
Question 13:
Can an artwork consist of multiple separately moored floating elements? Are there specific requirements or preferred approaches for tethering to minimize entanglement or navigation hazards?
Answer 13:
Multiple anchored elements are permitted, provided they do not create navigation or entanglement hazards. There is no prescribed tethering method. The final anchoring and tethering system will depend on the proposed artwork and applicable marine engineering requirements.
Question 14:
What criteria should applicants consider when designing the artwork to ensure it is not easily climbable?
Answer 14:
There is no prescribed dimensional standard for climbability. The artwork should be designed to discourage people from climbing onto or accessing it from the water.
Question 15:
Can required warnings against climbing or tampering be integrated into the artwork or its graphics, provided they are clearly visible and legible?
Answer 15:
Safety warnings may be integrated into the artwork’s graphics, provided they are clearly visible and legible on approach.
Question 16:
Is a floating or illuminated perimeter, similar to that shown in Appendix C, required, recommended or optional? If used, are there requirements for its placement or distance from the artwork?
Answer 16:
Safety buoys or markers will be required as appropriate to the artwork and its configuration. Final requirements will be determined through navigation and safety review.
Question 17:
Can required navigation lights be located on perimeter markers or buoys rather than directly on the artwork? Are there requirements for the number, colour, flash pattern, visibility range or operating hours of the lights?
Answer 17:
Section 2.2.1 requires navigation safety lighting but does not prescribe the number, colour, flash pattern, visibility range or fixture type. Final requirements will be subject to safety and navigation review by the Harbour Master’s office and other relevant authorities.
Question 18:
Should applicants include an allowance in the project budget for perimeter buoys, markers or other navigation safety measures?
Answer 18:
Artists should include an allowance in the project budget for required safety buoys or markers. Final requirements will depend on the selected artwork and navigation and safety review.
Question 19:
Can the artwork incorporate low-level lighting for nighttime viewing, including solar-powered lighting? Are there requirements or limitations related to brightness, colour or light pollution?
Answer 19:
Lighting must be included as part of the proposal and the artwork must be lit through the night. Proposed lighting must be suitable for the marine environment and should minimize light pollution and disturbance to nearby residents.
Question 20:
Who is responsible for routine cleaning and maintenance of the artwork during the exhibition period, and is a minimum maintenance frequency required?
Answer 20:
The artist team is responsible for maintaining the artwork throughout the exhibition period and should budget accordingly. There is no prescribed cleaning schedule. The artwork must be accessible by boat where inspection or maintenance is required.
Question 21:
If a proposal is selected and final engineering requirements or contractor costs differ from the preliminary estimates submitted, can funds be reallocated between project budget line items, provided the total project budget remains within $100,000 CAD + HST?
Answer 21:
Yes. Preliminary estimates are sufficient at the proposal stage, and the project budget may be refined as engineering requirements and firm pricing are developed following selection. Funds may be reallocated between budget line items, subject to Waterfront Toronto’s review and approval, provided the total project budget does not exceed $100,000 CAD + HST.
Question 22:
Is all-risk insurance required at the proposal stage, or only following selection as part of the final contract requirements?
For proposal-stage budgeting, how should applicants estimate the cost of the required insurance coverage, including all-risk insurance?
Answer 22:
Final insurance documentation is not required at the proposal stage. Applicants should include an appropriate insurance allowance in the project budget based on the requirements outlined in the RFP. Preliminary estimates are acceptable for budgeting purposes.
Please refer to Addendum #2 for further clarification on the insurance requirements and required coverage.
Question 23:
Does the $100,000 CAD + HST commissioning budget include the artist fee and all project-related expenses? Is the recommended allowance of approximately $10,000 CAD, plus contingency, for installation and removal also included within the $100,000 budget?
Answer 23:
Yes. The total commissioning budget is $100,000 CAD + HST, and all project costs, including the artist fee, engineering, insurance, fabrication, installation and removal, must fit within the $100,000 + HST. The recommended installation/removal allowance and contingency are also included within this amount.
Question 24:
Can Waterfront Toronto’s project signage include a link or QR code directing visitors to an artist-hosted webpage about the artwork?
Answer 24:
Waterfront Toronto will provide standard on-site signage for the project. Any additional content proposed by the artist, including a web link or QR code, will be subject to Waterfront Toronto’s review and approval. Please refer to Addendum #2 for further clarification on signage requirements.
Question 25:
Can artists propose the preferred location and orientation of the artwork within the basin as part of their submission, subject to navigation, safety and technical requirements?
Answer 25:
Yes, artists may propose the location and orientation of the artwork within the basin, subject to technical, safety and navigation requirements.
Question 26:
What site access and staging options are available for installation of the artwork?
Can the artwork be assembled or launched from the basin edge, including where lifting or other installation equipment may be required; specifically a boom truck or a crane stage?
Answer 26:
In previous years, artists have used methods like a barge as part of their installation plans, including for Global Convenience. Assembly while afloat or at the basin edge may be considered, subject to feasibility and safety requirements. Artists should outline their proposed installation approach in their submission. Waterfront Toronto will work with the selected artist and installation team to refine the plan and coordinate necessary approvals.
Question 27:
Who will determine the final requirements for navigation safety lighting, including the number, colour and type of lights, and is the artist team responsible for providing them?
Following selection, will Waterfront Toronto facilitate the required reviews and approvals with the Harbour Master’s office, the City and other relevant authorities?
Answer 27:
Navigation safety lighting is required, and additional safety markers may be required depending on the artwork. Waterfront Toronto will work with the selected artist to ensure all approvals from our various partners are obtained prior to installation.
Public Art Department, Waterfront Toronto